Construction season is here and so is our weekly look at what projects are done, where you’ll find traffic impacts and what’s scheduled next.

What’s done

57th Street: The asphalt overlay on 57th Street between Louise and Oxbow avenues is complete and open to traffic!

Pavement striping will occur within the next few weeks outside of peak traffic hours; however, traffic delays should be expected while crews are applying the pavement markings.

What’s underway

I-229 & Benson: Work at the Benson Road/Interstate 229 interchange is nearing completion! Concrete paving is complete along Benson and nearing completion on the interstate ramps.

The northbound off-ramp from I-229 to Benson is expected to reopen to traffic later this week or next week.

Other work occurring includes traffic signal installation, restoration/landscaping and construction of the channelizing islands.

The interchange is expected to be fully open in the diverging diamond configuration in mid-to-late October and will feature the city’s first triple left turn lane from northbound I-229 onto westbound Benson Road.

31st Street: Work is underway to reconstruct one block of 31st Street between Minnesota and Spring avenues.

Work includes replacement of a sanitary sewer manhole, storm drainage pipe installation, construction of a detention basin on a city-owned lot along Spring Avenue, accessible curb ramp improvements, new sidewalk and curb and gutter, asphalt paving and regrading of an alley.

Work is expected to be complete later this fall.

Minnesota Avenue: The outside southbound lane on Minnesota Avenue closed between 77th and 81st streets Sept. 25 to allow crews to repair a driveway approach. This work is expected to be complete in about two weeks.

I-90: The Interstate 90 eastbound Exit 379 on- and off-ramps at Humboldt closed Sept. 28 to allow crews to perform concrete paving. This work is expected to be complete in about one week.

What’s next

Beginning today:

  • Lane closures will be in place on Interstate 29 from mile markers 84 to 85, near I-90, and from mile markers 76 to 79 , from 57th to 12th streets, to allow crews to perform pavement repairs. This work is expected to be complete in about three weeks.
  • The outside northbound lane of Western Avenue will be closed between 63rd Place and 57th Street to allow crews to perform sidewalk repairs. This work is expected to be complete in about two days.
  • Crews will be performing repairs to the sanitary sewer on Prairie Avenue between 13th and 15th streets. There will be intermittent short-term lane restrictions, short-term road closures, driveway access restrictions and street parking restrictions as the work progresses.  This work is expected to be complete in about one week.
  • The outside westbound and eastbound lanes on River Boulevard will be closed at the Big Sioux River bridge to allow crews to perform sidewalk repairs. This work is expected to be complete in one day.

Beginning Tuesday:

  • The outside eastbound lane of 69th Street will be closed between Doral Trail and Inverness Drive to allow crews to perform sidewalk repairs. This work is expected to be complete in one day.
  • Bahnson Avenue will be closed between 36th and 41st streets to allow crews to replace a fire hydrant. This work is expected to be complete in one day.

Beginning Wednesday:

  • The outside westbound lane of 69th Street will be closed between Inverness Drive and Doral Trail to allow crews to perform sidewalk repairs. This work is expected to be complete in one day.

TAGS:

Share This Story

Most Recent

Videos

Instagram

Hope you had a wonderful summer weekend and are recharged for the week ahead! 📸: @jpickthorn
Favorite flyover of the year! Merry Christmas from our entire @pigeon605news flock. 🎄🐦 📸: @actsofnaturephotography
Happy Halloween from @avera_health NICU babies! Link in bio to see more! 🎃
Did you know @dtsiouxfalls is filled with 👻 stories? Link in bio … if you dare 😱

Want to stay connected to where you live with more stories like this?

Adopt a free virtual “pigeon” to deliver news that will matter to you.

Are you a little bird with something to share?