Road Report: Aug. 14, 2023

Pigeon605 Staff

August 14, 2023

Construction season is here, and so is our weekly look at what projects are done, where you’ll find traffic impacts and what’s scheduled next.

What’s done

Arrowhead Parkway: All lanes of traffic on Arrowhead Parkway near Six Mile Road are open to traffic!

There still might be some periodic daytime lane closures set up as the contractor finishes a few remaining work items and cleans up the area. Check out how it turned out:

What’s underway

Phillips Avenue: On Aug. 9, Phillips Avenue closed between Falls Park Drive and North Drive to allow crews to perform street maintenance. This work is expected to be complete in about three weeks.

26th Street: Work is in progress along 26th Street between Cleveland and Alpine avenues.

The contractor is upgrading the accessible curb ramps on the north side of the street ahead of an asphalt overlay.

Traffic is reduced to one lane in each direction throughout the work area.  Work on this project won’t be complete until mid-November.

Unity Bridge & Sixth Street: Progress continues on the Unity Bridge and Sixth Street in downtown Sioux Falls.

Falsework construction for the bridge is about 75 percent complete.

Crews have begun pouring the new concrete surfacing east of the bridge.

The bore pits also are being excavated in preparation to bore under the railroad tracks for the underground utility duct bank.

At one point last week, there were six subcontractor crews working on-site!

What’s next

The following projects are all scheduled to start today:

Ellis Road: The outside northbound lane on Ellis Road will be closed at the intersection of 26th Street to allow crews to perform a concrete repair. One northbound lane of traffic will be maintained at all times during construction. Southbound traffic will not be impacted by this work. This work is expected to be complete in about one week.

Ellis Road: The outside southbound lane on Ellis Road will be closed south of 22nd Street to allow crews to perform a concrete repair. One southbound lane of traffic will be maintained at all times during construction. Northbound traffic will not be impacted by this work. This work is expected to be complete in about one week.

Veterans Parkway: The outside southbound lane and the right turn lane on Veterans Parkway will be closed north of Madison Street to allow crews to perform a concrete repair. One southbound lane of traffic will be maintained at all times during construction. Northbound traffic will not be impacted by this work. This work is expected to be complete in about one week.

Veterans Parkway: The outside southbound lane and shoulder area on Veterans Parkway will be closed south of Maple Street to allow crews to perform a concrete repair. One southbound lane of traffic will be maintained at all times during construction. Northbound traffic will not be impacted by this work. This work is expected to be complete in about one week.

I-229 at Western: The northbound on-ramp from Western Avenue to Interstate 229 will be closed to allow crews to widen the on-ramp. This work is expected to be complete in November.

I-229 at Minnesota: The northbound off-ramp from Interstate 229 to Minnesota Avenue will be closed to allow crews to perform concrete repairs. This work is expected to be complete in about one week.

Marion: The outside northbound lane on Marion Road will be closed on either side of 41st Street to allow Xcel Energy to work on new electrical lines. The outside westbound lane on 41st also will be closed just east of Marion as part of this work. This work is expected to be complete in about one month.

Ninth & Duluth: The intersection of Ninth Street and Duluth Avenue will be closed to allow crews to install a traffic circle. This work will be completed later this summer.

10th Street: The outside eastbound lane of 10th Street will be closed between Cliff and Chicago avenues to allow crews to perform sidewalk repairs. This work is expected to be complete in about one week.

57th Street: The outside eastbound lane and a portion of the right turn lane on 57th Street will be closed east of Rolling Green Avenue to allow crews to work on new utilities. This work is expected to be complete in about two weeks.

Sixth Street: Sixth Street will be closed west of Minnesota Avenue to allow crews to work on gas lines. A detour will be in place. This work is expected to be complete by the end of the day.

Minnesota Avenue: Beginning on Tuesday, the northbound shoulder of Minnesota Avenue will be closed between Benson Road and 60th Street North to allow crews to install a new underground power line. Traffic will be maintained in both directions at all times, but equipment will be parked along the shoulder. This work is expected to be complete in about two weeks.

TAGS:

Share This Story

Most Recent

Videos

Instagram

Hope you had a wonderful summer weekend and are recharged for the week ahead! 📸: @jpickthorn
Favorite flyover of the year! Merry Christmas from our entire @pigeon605news flock. 🎄🐦 📸: @actsofnaturephotography
Happy Halloween from @avera_health NICU babies! Link in bio to see more! 🎃
Did you know @dtsiouxfalls is filled with 👻 stories? Link in bio … if you dare 😱

Want to stay connected to where you live with more stories like this?

Adopt a free virtual “pigeon” to deliver news that will matter to you.

Are you a little bird with something to share?